11 Jan 2007
| Course Overview | A description of the course structure, the project, and the expectations for each team.
|
 | A description of the project specifications.
|
 | An overview of the software development strategy.
|
|
18 Jan 2007
| Fundamentals of RF Design
Special presentation on RF front-end design by Professor Michael Jensen.
|
25 Jan 2007
| Real-Time DSP Programming Tips
Topics include sine/cosine look-up tables and circular addressing, code optimization, memory management, code profiling to find the critical path, DMA control.
Presented by Prof. Brian Jeffs.
|
| |
8 Feb 2007
| First Design Review
This is a 15 minute presentation where you provide a detailed review of your design. Information should include
 | A summary of your Functional Specification. Part of your grade will be how well you came to meeting these specifications.
|
 | A summary of your Concept Generation and Selection Include a brief description of the different approaches you considered, a brief description of the criteria you applied to identify the best approach, and a detailed description of your selected approach.
|
The detailed description should focus on two key aspects:  | Complete RF front-end design. At a minimum you should demonstrate filter specificaitons, analysis of adjacent channel interference, noise, and image rejection levels, knowledge of the external RF environment, hardware parts list, and a detailed block diagram, schematic, and chasis layout.
|
 |
A working MATLAB demonstration. Demonstrate the operation on one of the provided data files.
Provide a DSP loading estimate including count of the number of multiples and adds per second, estimate of the required level of optimization on the DSP processor (amount of parallelization).
Identify (in code) data debug test points and what signals should look like (debug tools).
|
|
22 Feb 2007
| Milestone 1: Software DemonstrationsDSP matched filter demonstration:  | Connect the I-Q Baseband outputs of the ESG-D Signal Generator to the A/D converter inputs on the TI EVM.
|
 | Direct the digital matched filter outputs to the D/A converters on the on the TI EVM.
|
 | Connect the TI EVM D/A converter outputs to the digital oscilloscope for display.
|
 | The synchronizer loops do not need to be working. But include a fixed phase rotation in your DSP code as a place holder for the carrier phase synchronization PLL.
|
|
1 Mar 2007
| Preliminary RF Hardware Demonstration
The demonstration should focus on the following:
 | The printed circuit board: the printed circuit board should already be fabricated and in-hand. It may not be populated yet.
|
 | Demonstrate the subsystems that are workking.
|
 | Parts: You should have many of your parts already in hand. Others may still be on order. Show that you have a reasonable delivery schedule.
|
 | A discussion of any open issues related to your RF design.
|
 | A detailed description of the RF front-end test and evaluation procedures.
|
 | A detailed back-up design.
|
|
8 Mar 2007
| Second Design ReviewThis is a 15 minute presentation followed by a 15 minute question-and-answer period. In this second design review, you should provide the following information:  | A detailed description of your schedule.
|
 | A cost estimate. (Show your calculations.)
|
 | A description of your progress to date relative to the milestones. (You should provide convincing evidence that your schedule will allow you to meet the deadlines for Milestones 2, 3, and 4.)
|
 | An update on your progress on the DSP code development.
|
 | An update on your progress on the RF hardware development.
|
 | A description of the changes that have been made in the design identified in the first design review.
|
|
15 Mar 2007
| Milestone 2: RF Hardware Demonstration | Minimum Requirements  | The complete RF system design including part numbers, printed circuit board layout, and a full schematic.
|
 | A detailed analysis of the RF system including gains, losses, noise figures, etc.
|
 | A realistic plan for completion (if the RF system is not already fully functional).
|
|
 | Also Demonstrate  | Any working modules or subsystems (or the complete design if available).
|
 | Components in your possesion.
|
 | Completed printed circuit boards.
|
|
|
22 Mar 2007
| Milestone 3: DSP Code Demonstration  | Connect the I-Q Baseband outputs of the ESG-D Signal Generator to the A/D converter inputs on the TI EVM.
|
 | Direct the interpolated matched filter outputs to the D/A converters on the on the TI EVM.
|
 | Connect the TI EVM D/A converter outputs to the digital oscilloscope for display.
|
 | The AGC and symbol timing PLL should be working. It should be clear that the symbol timing PLL locks and that the AGC is working properly.
|
|
29 Mar 2007
| Interfacing with the Bit Error Rate Tester This presentation will introduce the basic operation of the bit error rate tester and how to interface with it.
|
5 Apr 2007
| Milestone 4: Fully Integrated System Demonstration | All DSP functions, including symbol timing recovery should be functioning. Output the downsampled and interpolated matched filter outputs through the TI EVM D/A converters to the digital oscilloscope. What should we see?
|
 | Demonstrate a fully integrated system: Antenna, RF front-end, and baseband DSP subsystem.
|
 | Although not required for this milestone, you should make sure your system can communicate with the bit error rate tester.
|
|
12 Apr 2007
| Senior Project Competitions | All senior project competitions will be held in conjunction with Industry Day. The competition will be in the evening in the Garden Court in the Wilkenson Center (ELWC). Food (pizza) will be provided in Room 3224 ELWC.
|
 | Judges (external engineers from industry) will be on hand to evaluate your designs.
|
 | Your 2-page brochure is due at 12:00 noon that day.
|
|
20 Apr 2007
| Final Report and Final Presentation 7:00 PM - 10:00 PM, 490 CB. (This is the final exam period for this course.) Final reports are due when you make your presentation.
|